TŜIDELDEL First Nation

PROJECTS

TŜIDELDEL First Nation

Client: TŜIDELDEL First Nation

Project Completion: 2023

https://www.tsideldel.org/


 

About the Project

Project Description

Tŝideldel First Nation undertook a rebuild and new build of approximately 8 kilometres of community subdivision road at Redstone Flat and Michel Gardens. The project included the design of new roads, upgrading existing roads to current design standards, paving of the high volume roads, and construction water and sewer infrastructure to support future housing needs in the community.

The planning, design, and approval phase of the project took several years and was approved for construction in 2022. Works began in the fall of 2022 and were completed in the fall of 2023. The road improvements increase safety in the community and reduce Operation and Maintenance requirement associated with the community roads.

 
Previous
Previous

Ts’uubaa-asatx Community Core

Next
Next

Snpink’tn (Penticton) Indian Band Community Core Master Plan