Main Waste Water Pumping Station
PROJECTS
Main Waste Water Pumping Station
Client: Town of Osoyoos
Project Completion: 2020
About the Project
Project Description
Approximately 98% of the Town’s sanitary gravity sewer terminates at the Main Waste Water Pumping Station, where it is then conveyed over 2km to the Town’s treatment lagoons.
The original station was constructed in 1966, replaced in 1978, and upgraded in 2000 (larger pumps) and 2013 (larger / twinned forcemain).
In 2012 the Town began looking at options for the replacement of the facility after identifying the current equipment and structure were nearing end of service life and would not be able to supply sufficient level of service in the coming decades.
The Town decided upon a facility consisting of:
Three Submersible Low-Lift Pumps
Two Rotary Drum Screens
Two Wash Presses
Three Vertical Turbine High Lift Pumps
3,500 cfm Odour Control Unit
Repurposing of existing 185hp High Lift Submersible Pumps as system redundancy
500kW Emergency Generator
260m² Precast Building with Cast-in-Place Foundation and 35m³ Wetwell